Week 7: Assignments
To do for next week:
- Flowchart of content and activities
- Goals 1 & 3 (Ahram, Remi)
- Goal 2 (HueiHsien, Kazu)
- Hardware/software specs edits (HueiHsien)
- Formative eval plan edits (Remi)
- Screen design (Daisy, Emily)
- Flowchart of online system (Emily)
- Group presentation PPT (Emily)
- Send to Holly, Duren (Emily)
- Task analysis
- Objectives
- User profile
- Review flowcharts for goals, system
- Review screen design
- Plan for
- future screen development
- distribution of graphic work
- storyboarding
- other items of interest....
- Flowchart, storyboards (Nov 1)
Posted by
EmBot
at
10:20 PM
0
comments
Labels: Project Management
Wednesday, September 26, 2007
Week 6
The ICC team has spent more time with the task analysis, performance objectives, and test items this week. After reviewing the ordered and somewhat revised content, a number of changes were needed to bring our tasks in line to the plant pathology content. The team has split into sub-groups to develop parts of this tasks and objectives. We will still request a review of this documentation before sending it to our client for sign-off.
Drafts of our formative evaluation plan, hardware/software specs, and user profile have been reviewed by our group, designated 6200 volunteer, and have been sent to Dr. Clinton for review.
An assignment list was not posted this week, although the following items were assigned:
- Ahram, Remi, Daisy review and develop tasks and objectives for:
- 1a. plant disease
- 1b. plant disease triangle
- 1c. pathogen groups
- 2a. communicating with clients
- 2c. sample collection
- Emily, HueiHsien, Kazu - review and develop tasks and objectives for:
- 1d. integrated pest management
- 2d. sample submission
- 2e. interpreting sample diagnoses and recommendations
- Myra review the following docs:
- Formative evaluation draft (Remi)
- User profile (Kazu)
- Notify 6200 consultants of duties, timelines
- Daisy develop screen design based on group direction in meeting
- Emily ask Duren about access to agents for evaluation
- Emily ask Holly about items for pre- and post-testing
Posted by
EmBot
at
5:13 PM
0
comments
Labels: Reports
Wednesday, September 19, 2007
Week 5
The team has been working on a number of documents this week, as outlined in our assignment list. Audra and Brent, two 6200 consultants, along with our SME Holly, have been helping Emily make the content more understandable and functional as lesson material.
- Project Scope - 9/16/07
- Needs Assessment- 9/17/07
Posted by
EmBot
at
4:48 PM
0
comments
Labels: Reports
Thursday, September 13, 2007
Week 5: Assignments
To do for next week:
By Thursday, September 20 (unless otherwise noted)
- Edit content - ASAP (Emily)
- Give to 6200 consultants for review with brief guidelines
- 6200 consultants review by 9/18, 5pm (flexible?)
- Send edited copy to team
- Project timeline: update timeline and brief report (Emily)
- Daisy send example to Emily
- Ahram help review
- Hardware/software specs: draft (HueiHsien)
- User profile: draft (Kazu)
- Emily send existing data to Kazu
- Formative evaluation plan: draft (Remi)
- Daisy to help
- Screen specs/treatment: design ideas (Daisy)
- Emily send web template screenshot
- Review content, bring ideas to next team meeting (all)
Team meeting, September 20:
- Clarify any unclear content areas
- Discuss content in context of screen specs and treatment, activities, etc.
- Start Screen Specs and Treatment Rationale docs as group in meeting
- Jobs for 6200 students (specifics or timeline of needs)
- Other items of interest...
Upcoming work: (to be reviewed and given to client)
See project management plan for suggested review process.
- Hardware/software specs
- Screen design specs
- Treatment rationale and description
- User profile
- Formative evaluation plan
- Use project activity logs
- Post completed documentation to blog
Posted by
EmBot
at
10:53 PM
0
comments
Labels: Project Management
Monday, September 10, 2007
Week 4: Project Documentation
Team Meeting
The team discussion centered on documentation and on the content analysis from the client. The projects’ Instructional goals and objectives were narrowed down.
Team divided required deliverables.
HueiHsien made changes to the Scope document
Kazu made changes to the Needs Analysis document
Ahram Daisy and Remi continued development of the Objectives and Task analysis.
To do for next week: By Tuesday, September 18
Submission of earlier documents to Client for approval
User profile
Treatment Rationale and Description
Hardware/Software Specifications
Screen design Specifications
Formative Evaluation Plan
Posted by
Oluremilekun Ojo
at
10:06 PM
0
comments
Labels: Reports
Tuesday, September 4, 2007
Week 3: Scope and Needs
The team has been collaborating on the scope document and needs assessment. We've determined a design for our documentation and divyyed up tasks among our group. Remi has taken the place of PM in Emily's absence. Duren has been contacted with a brief timeline of upcoming reports and notification of our current progress.
Our tasks for this week can be seen here:
Week 3: Assignments
(note - this entry is backdated to fit into our timeline.)
Posted by
EmBot
at
12:00 AM
0
comments
Labels: Reports